This project was a design build
project. We designed and installed the fuel system as a 2N design with
complete separate systems that are thus fully redundant. Our fuel system supports
six 2.0 megawatt generators and two 500kw generators with two 25,000 gallon underground
storage tanks, redundant pumps, redundant power supplies and redundant piping
paths. All piping on the project is double contained. The fuel control
system is PLC based, complete with fully developed modbus interface to the BAS
system. This project was awarded at a preference due to the superior design
and greatest value (not lowest cost).
|
|
 |
|